A semi-variable cost was $14,000 at 2,000 units and $20,000 at 5,000 units. Using the high-low method, what is the budgeted cost at 4,000 units?

The budgeted cost is $18,000. The high-low method gives a variable cost of $2 per unit and fixed cost of $10,000, so at 4,000 units the cost is $10,000 plus $8,000.

  1. A$18,000Correct
  2. B$16,000
  3. C$17,000
  4. D$19,000

Explanation

Variable rate = (20,000 - 14,000)/(5,000 - 2,000) = $2 per unit. Fixed element = 20,000 - 5,000 x 2 = $10,000. Cost at 4,000 units = 10,000 + 8,000 = $18,000. Check at 2,000: 10,000 + 4,000 = 14,000.