A factory worker is paid a basic rate of $12 per hour for a 40-hour week. Hours worked in excess of 40 are paid at time-and-a-half. In one week the worker works 46 hours, of which 4 hours of overtime were spent on a specific customer's urgent job at the customer's request. How much of the total pay should be treated as a direct labour cost of the urgent job?

The full overtime cost of $72 (4 hours at $18) is a direct cost of the urgent job, because overtime worked specifically at a customer's request is charged entirely to that job, including the premium, rather than to general overheads.

  1. A$72.00 only for the premium element
  2. B$48.00 for basic pay only
  3. C$72.00 for the full overtime cost (4 hours at $18)Correct
  4. D$216.00 for all overtime hours worked

Explanation

Overtime requested by a customer for a specific job is charged directly to that job, both basic pay and premium. 4 hours x $18 = $72. The premium-only treatment ($24 premium) is for general overtime and would be wrong here, and the 6 hours at $18 option includes hours not for this job.

Did you get it right without looking?