A factory's machine shop budgeted overheads of Rs 4,80,000 for the year and 24,000 machine hours. Actual overheads were Rs 5,10,000 and actual machine hours were 25,000. Using a predetermined machine hour rate, what is the overhead absorbed by the machine shop?

Overhead absorbed is Rs 5,00,000. The predetermined rate is budgeted overheads divided by budgeted machine hours, which is Rs 20 per hour, and this is applied to the actual 25,000 hours worked. Actual overhead incurred does not affect the amount absorbed.

  1. ARs 4,80,000
  2. BRs 5,00,000Correct
  3. CRs 5,10,000
  4. DRs 5,25,000

Explanation

Predetermined rate = 4,80,000 / 24,000 = Rs 20 per machine hour. Absorbed = 25,000 x 20 = Rs 5,00,000. Rs 5,10,000 is wrong because it is actual overhead, not absorbed overhead, and Rs 4,80,000 uses the budgeted total.

Did you get it right without looking?

One question tells you little. A timed set on Overheads - Absorption Costing Method shows your real accuracy, how long you take and where you lose marks.

More Overheads - Absorption Costing Method questions