CA Intermediate · Financial Management and Strategic Management · Investment Decisions

A firm has ₹5,00,000 available for capital rationing and the following indivisible projects: P (outlay ₹3,00,000, NPV ₹60,000), Q (outlay ₹2,00,000, NPV ₹50,000), R (outlay ₹2,50,000, NPV ₹40,000). Which combination maximises total NPV?

The best combination is P and Q with a total NPV of ₹1,10,000. Together they cost exactly ₹5,00,000, within the budget. P and R would cost ₹5,50,000 and is not feasible, while Q and R yields only ₹90,000.

  1. AP and Q, total NPV ₹1,10,000Correct
  2. BP and R, total NPV ₹1,00,000
  3. CQ and R, total NPV ₹90,000
  4. DOnly P, total NPV ₹60,000

Explanation

Feasible combinations within ₹5,00,000: P+Q costs 5,00,000 (NPV 1,10,000); Q+R costs 4,50,000 (NPV 90,000); P+R costs 5,50,000 and exceeds the budget, so it is infeasible. P+Q gives the highest NPV. The P+R option is wrong because it breaches the budget.