CA Intermediate · Cost and Management Accounting · Employee Cost and Direct Expenses
A firm pays Rs 25 per hour for normal time and double rate for overtime beyond 8 hours a day. A worker works 10 hours on a day due to an urgent customer order that was specifically requested by the customer. How should the overtime premium be treated in costing?
The overtime premium should be charged directly to the specific job. Because the customer specifically requested urgent work, the extra premium is attributable to that job. Overtime from general pressure goes to factory overheads, and abnormal overtime goes to costing profit and loss account.
- ACharged to the specific job as direct costCorrect
- BCharged to factory overheads for all jobs
- CCharged to costing profit and loss account
- DCharged to administration overheads
Explanation
If overtime is required by a customer's specific request, the overtime premium is charged to that job. If it arises from general production pressure it is a factory overhead; if due to abnormal causes it goes to costing profit and loss account. Here the customer requested it, so the job bears it.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- Which one of the following is an example of 'idle time' in the context of employee cost?
- Kapoor Fabrics has a skilled workman who produces 120 units in a 50-hour week. The standard output is 2 units per hour. He is paid under the…
- In a cost accounting context, which one of the following is classified as 'idle time' of a worker?
- Which of the following is treated as an employee cost that is NOT directly traceable to a specific cost unit, and is therefore normally clas…
- Which of the following is treated as an indirect employee cost in a manufacturing company and therefore included in factory overheads?
- Under the Rowan plan, a worker has a time rate of Rs 30 per hour, standard time of 60 hours and actual time taken of 45 hours. What is the t…