CA Intermediate · Cost and Management Accounting · Employee Cost and Direct Expenses
Anand Engineering has 200 workers on average during a year. During the year 18 workers left, 6 were discharged and 16 new workers were recruited, of whom 10 were replacements for those who left or were discharged. Using the replacement method, what is the labour turnover rate?
Labour turnover by the replacement method is 5%. Only 10 workers were recruited as replacements, and dividing 10 by the average strength of 200 gives 5%. Additional recruits and total separations are not counted under this method.
- A5%Correct
- B8%
- C12%
- D3%
Explanation
Replacement method: workers replaced / average workers x 100. Ten workers were replaced, so 10/200 x 100 = 5%. The separation method would give 24/200 = 12%, and the flux method would give (24+16)/200 = 20%. The 8% option uses all 16 recruits, which wrongly includes additions.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- Meenakshi Textiles pays a skilled worker Rs 120 per hour for a 48-hour week. Normal week is 40 hours. Overtime beyond 40 hours is paid at do…
- A worker at Sharma Engineering is paid under the Halsey premium plan. The standard time for a job is 40 hours, the time rate is Rs 60 per ho…
- Which one of the following is an example of 'idle time' in the context of employee cost?
- Which of the following is a method of wage payment in which a worker's earnings are guaranteed at a minimum time-rate, with a bonus paid onl…
- Sunrise Pharma's worker earns Rs 100 per hour. A bonus is credited under a group scheme, and he works 8 hours a day for 26 days in a month, …
- Gupta Textiles had an annual labour turnover where 24 workers left and 6 were replaced due to expansion (additional posts), while 18 were re…