FRM Part II · FRM Exam Part II · Estimating Market Risk Measures: An Introduction and Overview
A firm uses historical simulation with a 500-day window to estimate 1-day 99% VaR. A risk officer wants the VaR estimate to be more precise at the 99% level without changing the confidence level. Which action most directly reduces the sampling error of the estimate?
Lengthening the window reduces sampling error because more observations fall in the tail beyond the 99% quantile. With 500 days only about five observations determine VaR; shortening the window would worsen precision, and horizon scaling does not address it.
- AShortening the window to 100 days so only recent data is used
- BLengthening the window so more observations lie in the tailCorrect
- CMultiplying the VaR by the square root of 10
- DReplacing the loss quantile with the median loss
Explanation
The 99% estimate relies on very few tail observations (5 of 500). A longer window increases the number of tail observations, reducing sampling error, though it may slow responsiveness. A 100-day window leaves only 1 tail observation. Square-root-of-time scaling changes the horizon, not precision.
Did you get it right without looking?
One question tells you little. A timed set on Estimating Market Risk Measures: An Introduction and Overview shows your real accuracy, how long you take and where you lose marks.
More Estimating Market Risk Measures: An Introduction and Overview questions
- A risk analyst uses 500 daily P&L observations to estimate 1-day 95% historical simulation VaR. Which statement best describes how the estim…
- A risk analyst plots the quantiles of a sample of daily portfolio returns (vertical axis) against the quantiles of a standard normal distrib…
- A risk analyst estimates one-day historical-simulation VaR from the same 1,000-day return sample at both the 95% and the 99% confidence leve…
- A risk committee compares two risk-aversion profiles for an exponential spectral risk measure, with risk-aversion coefficient k. Moving from…
- A bank wants a risk measure that reflects a manager's subjective risk aversion while remaining subadditive. It considers a spectral measure …
- A risk manager notes that an exponential spectral risk measure becomes much larger when the risk-aversion coefficient is increased. What is …