A multiple activity chart for a Pune workshop shows that in a 10-minute cycle, the operator works for 6 minutes and is idle for 4 minutes, while the machine works for 5 minutes and is idle for 5 minutes. If a changed method makes the cycle 8 minutes by overlapping 2 minutes of the operator's idle time with the machine's run time, with the operator's working time and the machine's running time staying unchanged, what is the new machine utilisation and operator utilisation?
Machine utilisation becomes 62.5% and operator utilisation becomes 75%. Both are calculated by dividing the unchanged working times, 5 minutes for the machine and 6 minutes for the operator, by the new 8-minute cycle time.
- AMachine 62.5%; operator 75%Correct
- BMachine 50%; operator 60%
- CMachine 62.5%; operator 60%
- DMachine 75%; operator 62.5%
Explanation
With the new 8-minute cycle, machine utilisation = 5/8 = 62.5%. Operator utilisation = 6/8 = 75%. Check: the operator idle time becomes 2 minutes and the machine idle time becomes 3 minutes, which sum correctly with the working times to the 8-minute cycle. The 50% and 60% option pair uses the old 10-minute cycle.
Did you get it right without looking?
One question tells you little. A timed set on Control Measures - Time and Motion Study, Method Study, Work Study shows your real accuracy, how long you take and where you lose marks.
More Control Measures - Time and Motion Study, Method Study, Work Study questions
- In the basic procedure of method study, which step comes immediately after 'Record' the relevant facts of the existing method?
- In a time study, a worker's observed performance is judged to be 120% against the standard (normal) rating of 100. The mean observed time fo…
- A flow process chart of a component records: 6 operations, 3 inspections, 4 transports, 2 delays and 1 storage. What is the total number of …
- In a micro-motion study of an assembly task filmed at 1,000 frames per minute, a cycle is recorded as 2,400 frames. A study of the same cycl…
- Which chart is most suitable for recording the movements of the left and right hands of a worker performing a bench assembly task, so that t…
- In a time study at a Pune auto-component unit, the average observed time for an element is 2.00 minutes and the operator's performance ratin…