FRM Part II · FRM Exam Part II · Estimating Market Risk Measures: An Introduction and Overview
A portfolio has 200 daily historical P&L observations. The five worst losses (in USD thousands) are 410, 350, 320, 290 and 260, and the sixth worst is 240. Using the convention that VaR at 97.5% confidence is the loss at the 5th worst observation (5 of 200 = 2.5% tail), and expected shortfall is the average of the tail losses beyond and including that tail set of 5 observations, what is the expected shortfall?
Expected shortfall is 326 thousand USD. It is the average of the five tail losses (410, 350, 320, 290, 260), which sum to 1,630, divided by 5. The figure 260 is only the VaR cutoff, not the tail average.
- A260
- B326Correct
- C294
- D410
Explanation
The tail set is the five worst losses: 410, 350, 320, 290, 260. Sum = 1,630; divided by 5 = 326. Choosing 260 gives the VaR, not ES. Using 4 observations gives 342.5, and averaging with the sixth gives 311.7. The 410 figure is only the maximum loss.
Did you get it right without looking?
One question tells you little. A timed set on Estimating Market Risk Measures: An Introduction and Overview shows your real accuracy, how long you take and where you lose marks.
More Estimating Market Risk Measures: An Introduction and Overview questions
- A risk committee compares two risk-aversion profiles for an exponential spectral risk measure, with risk-aversion coefficient k. Moving from…
- A bank wants a risk measure that reflects a manager's subjective risk aversion while remaining subadditive. It considers a spectral measure …
- A risk manager notes that an exponential spectral risk measure becomes much larger when the risk-aversion coefficient is increased. What is …
- A risk analyst wants a standard error and confidence interval for a 99% expected shortfall estimated from 750 historical returns, without as…
- A risk manager compares the 99% 1-day VaR from historical simulation using 1,000 days of data against a parametric normal VaR. Which stateme…
- Two independent bonds each have a 4% chance of a USD 100 million loss and a 96% chance of zero loss. A risk manager computes the 95% VaR of …