A portfolio has exposures to three principal components. The factor standard deviations are 6 bp (PC1), 3 bp (PC2) and 1 bp (PC3). The portfolio's dollar value changes are 50,000 per bp for PC1, 40,000 per bp for PC2 and 100,000 per bp for PC3. Treating the components as uncorrelated, what is the portfolio's standard deviation of value change?

Multiply each exposure by its factor volatility to get 300,000, 120,000 and 100,000. Since components are uncorrelated, combine them as the square root of the sum of squares, about 338,000, so roughly 335,000. Adding them linearly would overstate risk by assuming perfect correlation.

  1. AApproximately 335,000Correct
  2. BApproximately 450,000
  3. CApproximately 300,000
  4. DApproximately 523,000

Explanation

Contributions: PC1 = 50,000×6 = 300,000; PC2 = 40,000×3 = 120,000; PC3 = 100,000×1 = 100,000. Because components are uncorrelated, add squares: 90,000,000,000+14,400,000,000+10,000,000,000 = 114,400,000,000 ... sqrt ≈ 338,230. Nearest option is 335,000. Simple summing (520,000) wrongly assumes perfect correlation.

Did you get it right without looking?

One question tells you little. A timed set on Regression Hedging and Principal Component Analysis shows your real accuracy, how long you take and where you lose marks.

More Regression Hedging and Principal Component Analysis questions