FRM Part II · FRM Exam Part II · Regression Hedging and Principal Component Analysis
A portfolio manager holds a position whose DV01 is USD 50,000 and wants to hedge it using a Treasury futures contract with DV01 of USD 800 per contract. Assuming a parallel yield shift and a one-to-one yield beta, how many contracts should be traded?
Sell 62.5 contracts. The hedge ratio equals the position DV01 divided by the futures DV01, 50,000 divided by 800. The position is long duration, so the futures must be sold to offset losses when yields rise.
- ASell 40 contracts
- BSell 62.5 contractsCorrect
- CSell 400 contracts
- DBuy 62.5 contracts
Explanation
Single-instrument DV01 hedge: contracts = 50,000 / 800 = 62.5. Because the position loses value when yields rise, the hedge is a short futures position. Dividing the wrong way or using a wrong scale gives 40 or 400, and buying would double the exposure.
Did you get it right without looking?
One question tells you little. A timed set on Regression Hedging and Principal Component Analysis shows your real accuracy, how long you take and where you lose marks.
More Regression Hedging and Principal Component Analysis questions
- In a PCA of a yield curve's rate changes, the first three components are typically interpreted as level, slope and curvature. A portfolio ma…
- A portfolio has total variance of 100 (bp² units). PCA of the risk factors shows the first component loading gives portfolio variance of 70 …
- A portfolio manager hedges a bond position using a regression of yield changes on a hedging instrument's yield changes. The regression has a…
- A risk manager is deciding how many principal components to retain when hedging a bond portfolio against yield curve moves. Which approach i…
- A trader holds a butterfly position that is long the 5-year bond, and short equal-risk amounts of the 2-year and 10-year bonds, constructed …
- A risk analyst applies principal component analysis (PCA) to the covariance matrix of daily changes in six par swap rates. Which statement a…