A project requires an outlay of ₹1,00,000 now and pays ₹60,000 at the end of each of the next two years. Using a discount rate of 10% per annum effective, what is the net present value of the project?
The NPV is ₹4,132.23. Discount each ₹60,000 inflow at 10%, giving a present value of about ₹1,04,132.23, then subtract the ₹1,00,000 outlay. The positive result means the project earns more than 10%.
- A₹1,04,132.23
- B₹4,132.23Correct
- C₹1,403.13
- D₹20,000.00
- -₹4,132.23
Explanation
NPV = 60,000 × (1/1.1 + 1/1.21) − 1,00,000 = 60,000 × 1.735537 − 1,00,000 = 1,04,132.23 − 1,00,000 = 4,132.23. The figure ₹1,04,132.23 is only the present value of the inflows and omits the outlay. ₹1,403.13 comes from discounting at 12% instead of 10%.
Did you get it right without looking?
One question tells you little. A timed set on Project appraisal shows your real accuracy, how long you take and where you lose marks.
More Project appraisal questions
- Which one of the following statements about payback and discounted payback is correct?
- For a project the net present value is +₹4,000 at 10% per annum and -₹1,000 at 15% per annum. Using linear interpolation between these two r…
- A project requires an outlay of Rs 1,000,000 now and returns Rs 1,200,000 exactly two years from now. The firm borrows at an effective annua…
- A project requires outlays of ₹10,000 at time 0 and ₹10,000 at time 1, and returns ₹23,100 at time 2. What is the IRR (effective annual)?
- A project costs Rs 200,000 now. It yields cash flows at the end of years 1 to 4 of Rs 60,000, then each later flow is 5% higher than the one…
- A project costs Rs 5,00,000 and yields Rs 1,00,000 at the end of each year for as long as required. At an effective annual rate of 8%, what …