A project requires an outlay of Rs 1,000,000 now and returns Rs 1,200,000 exactly two years from now. The firm borrows at an effective annual rate of 8%. What is the net present value of the project at 8% per annum?

The NPV is Rs 28,806.58. The Rs 1,200,000 received after two years is discounted at 8% for two years, giving Rs 1,028,806.58, and the Rs 1,000,000 outlay is then subtracted. The positive result means the project beats the cost of borrowing.

  1. ARs 28,806.58Correct
  2. BRs 111,111.11
  3. CRs 200,000.00
  4. D-Rs 47,401.30
  5. Rs 399,680.00

Explanation

NPV = 1,200,000 / 1.08^2 - 1,000,000 = 1,200,000 / 1.1664 - 1,000,000 = 1,028,806.58 - 1,000,000 = 28,806.58. Rs 111,111.11 discounts for only one year. Rs 200,000 ignores discounting. Rs 399,680 accumulates rather than discounts.

Did you get it right without looking?

One question tells you little. A timed set on Project appraisal shows your real accuracy, how long you take and where you lose marks.

More Project appraisal questions