A project's cash loss, if a risk event occurs, is Rs 40 lakh. The probability of occurrence is 15%. Management buys cover that will pay 70% of any loss for a premium of Rs 3 lakh. What is the expected net cost of the risk to the firm, including the premium?

The expected net cost is Rs 4.80 lakh. Expected loss is 15% of Rs 40 lakh, which is Rs 6 lakh. The insurer bears 70%, leaving Rs 1.8 lakh retained, and adding the Rs 3 lakh premium gives Rs 4.8 lakh.

  1. ARs 4.80 lakhCorrect
  2. BRs 3.00 lakh
  3. CRs 6.00 lakh
  4. DRs 7.80 lakh

Explanation

Expected loss = 15% x 40 = Rs 6 lakh. Insurance bears 70%, so retained expected loss = 30% of 6 = Rs 1.8 lakh. Add premium Rs 3 lakh to get Rs 4.8 lakh. Rs 6 lakh ignores the cover, and Rs 7.8 lakh wrongly adds the premium to the unhedged loss.

Did you get it right without looking?

One question tells you little. A timed set on Risk Management shows your real accuracy, how long you take and where you lose marks.

More Risk Management questions