CMA Final · Strategic Performance Management and Business Valuation · Risk Management
Aarav Textiles estimates that a fire could damage its warehouse stock. Probability of a fire in a year is 2%, and the loss if it occurs is Rs 50,00,000. Insurance cover costing Rs 80,000 per year would fully indemnify the loss. Based only on expected loss, what is the annual expected loss and the comparison with the premium?
Expected annual loss is Rs 1,00,000, obtained by multiplying the 2% probability by the Rs 50,00,000 loss. Since the Rs 80,000 premium is lower than this expected loss, insurance is financially attractive on an expected value basis.
- ARs 1,00,000; premium is lower than expected lossCorrect
- BRs 1,00,000; premium is higher than expected loss
- CRs 80,000; premium equals expected loss
- DRs 2,50,000; premium is lower than expected loss
Explanation
Expected loss = 2% x 50,00,000 = Rs 1,00,000. The premium of Rs 80,000 is below this, so on expected value alone insurance is favourable. Option with Rs 2,50,000 wrongly uses a different base.
Did you get it right without looking?
One question tells you little. A timed set on Risk Management shows your real accuracy, how long you take and where you lose marks.
More Risk Management questions
- Under the three lines model of risk governance, which activity is characteristically performed by the third line?
- In enterprise risk management, a firm decides to withdraw from a product line whose expected losses exceed the board's risk appetite, rather…
- A company expects Rs 10 crore of sales in USD next quarter and enters a forward contract to sell the dollars at a fixed rate. Which risk-man…
- In an enterprise risk management framework, a manufacturing firm decides to stop selling a product line in a politically unstable country be…
- Case: Kaveri Textiles has a portfolio worth Rs 50 crore. Daily returns are normally distributed with a mean of zero and a daily standard dev…
- Which risk is best described as the possibility of loss arising from inadequate or failed internal processes, people, systems or external ev…