A project's NPV depends on two independent variables. Sales volume is high (probability 0.6) or low (0.4). Selling price is high (probability 0.5) or low (0.5). The NPVs are: high volume/high price $100,000; high volume/low price $20,000; low volume/high price $10,000; low volume/low price -$60,000. What is the expected NPV?

The expected NPV is $26,000. Because volume and price are independent, the joint probabilities are 0.3, 0.3, 0.2 and 0.2. Multiplying each NPV by its joint probability gives 30,000, 6,000, 2,000 and -12,000, which total $26,000.

  1. A$26,000Correct
  2. B$17,500
  3. C$38,000
  4. D$36,000

Explanation

Joint probabilities are 0.30, 0.30, 0.20 and 0.20. EV = 30,000 + 6,000 + 2,000 - 12,000 = $26,000. $17,500 is the simple average of the four NPVs. $38,000 leaves out the loss-making outcome. $36,000 uses only the two extreme combinations with the volume probabilities (0.6 × 100,000 + 0.4 × -60,000).

Did you get it right without looking?

One question tells you little. A timed set on Adjusting for risk and uncertainty in investment appraisal shows your real accuracy, how long you take and where you lose marks.

More Adjusting for risk and uncertainty in investment appraisal questions