A project requires an initial outlay of $120,000 now. Net cash inflows are expected to be $30,000 in year 1, $50,000 in year 2, $40,000 in year 3 and $60,000 in year 4, arising evenly through each year. What is the payback period?
Payback is 3.0 years. Cumulative inflows reach $30,000, then $80,000, then $120,000 at the end of year 3, which exactly equals the initial outlay of $120,000, so no part of year 4 is needed.
- A3.0 yearsCorrect
- B3.33 years
- C3.17 years
- D2.80 years
Explanation
Cumulative cash flows: year 1 $30,000, year 2 $80,000, year 3 $120,000. The outlay is fully recovered exactly at the end of year 3, so payback is 3.0 years. The 3.33 option wrongly adds extra time from year 4.
Did you get it right without looking?
One question tells you little. A timed set on Adjusting for risk and uncertainty in investment appraisal shows your real accuracy, how long you take and where you lose marks.
More Adjusting for risk and uncertainty in investment appraisal questions
- Which of the following techniques is normally used to deal with uncertainty, rather than risk, in investment appraisal, because it does not …
- An investment costs $150,000 now. Annual cash inflows for four years are $40,000 (probability 0.25), $60,000 (probability 0.45) or $80,000 (…
- A project has an NPV of $80,000 with probability 0.5 and an NPV of $20,000 with probability 0.5. What is the standard deviation of the NPV?
- Which of the following is a recognised weakness of using the payback period as the only method of investment appraisal?
- A company's normal cost of capital is 10%. A project has a higher business risk than the company's existing operations, so management adds a…
- Kestrel Ltd is appraising a project with three possible outcomes. Its analyst has estimated the probability of each outcome from past experi…