A Pune firm purchases 12,000 units of a component per year. Ordering cost is Rs 300 per order and carrying cost is Rs 7.20 per unit per year. What is the Economic Order Quantity (EOQ)?

EOQ = sqrt(2 x 12,000 x 300 / 7.20) = sqrt(1,000,000) = 1,000 units.

  1. A600 units
  2. B1,000 unitsCorrect
  3. C1,200 units
  4. D2,400 units

Explanation

EOQ = sqrt(2 x annual demand x ordering cost / carrying cost per unit) = sqrt(2 x 12,000 x 300 / 7.20). Numerator = 7,200,000; dividing by 7.20 gives 1,000,000. The square root is 1,000 units. The other options do not satisfy the formula with the given data.