A regression of total monthly maintenance cost (y, in $) on machine hours (x) gives y = 4,200 + 3.5x. Machine hours next month are forecast at 2,000. What is the forecast maintenance cost?
The forecast cost is $11,200. Substitute 2,000 machine hours into the regression line: fixed cost of $4,200 plus variable cost of $3.50 per hour times 2,000 hours, which is $7,000, giving a total of $11,200.
- A$7,000
- B$11,200Correct
- C$4,203.5
- D$14,000
Explanation
Cost = 4,200 + 3.5 x 2,000 = 4,200 + 7,000 = $11,200. Option A omits the fixed cost of $4,200. Option D multiplies 7,000 by 2 in error or misuses the formula.
Did you get it right without looking?
One question tells you little. A timed set on Summarising and analysing data shows your real accuracy, how long you take and where you lose marks.
More Summarising and analysing data questions
- A company records the number of units produced per shift over ten shifts. Output was 10 units in 2 shifts, 20 units in 6 shifts and 30 units…
- A manager ranks four suppliers as 1st, 2nd, 3rd and 4th based on delivery reliability. What type of data is this ranking?
- Quarterly sales (000) of Alder Co were: Q1 120, Q2 150, Q3 130, Q4 140. Which of the following is the cumulative frequency-style running tot…
- A company finds that the correlation coefficient between monthly advertising spend and monthly sales revenue is +0.92. Which statement is th…
- In linear programming, what does the feasible region represent on a graph?
- A cost index rose from 200 to 230 between two years. What was the percentage increase in cost over that period?