A risk analyst uses Monte Carlo simulation to estimate the expected payoff of a derivative. With 10,000 independent simulated payoffs, the standard error of the estimated mean is 0.40. The analyst wants to cut the standard error to 0.10 by increasing the number of simulations only. How many simulations are required?
160,000 simulations are needed. Standard error falls with the square root of N, so reducing it fourfold from 0.40 to 0.10 requires sixteen times as many draws: 10,000 x 16 = 160,000. Quadrupling N to 40,000 would only halve the error.
- A40,000
- B80,000
- C160,000Correct
- D1,000,000
Explanation
Standard error is sigma divided by the square root of N. Cutting it by a factor of 4 (0.40 to 0.10) requires N to rise by 4^2 = 16. So N = 10,000 x 16 = 160,000. Choosing 40,000 wrongly scales N by the same factor as the error reduction.
Did you get it right without looking?
One question tells you little. A timed set on Simulation and Bootstrapping shows your real accuracy, how long you take and where you lose marks.
More Simulation and Bootstrapping questions
- A analyst applies the basic i.i.d. bootstrap to 500 daily returns of an asset whose returns show strong volatility clustering and positive a…
- A firm uses Monte Carlo simulation to value a portfolio, drawing correlated asset returns from a multivariate normal model calibrated in a c…
- A risk manager bootstraps daily returns of an asset by drawing individual returns independently with replacement, but the returns show stron…
- A firm plans to use Monte Carlo simulation to assess portfolio risk and generates scenarios from a model calibrated to a calm historical per…
- Compared with a Monte Carlo simulation that assumes returns follow a normal distribution, what is the principal advantage of the bootstrap f…
- A risk manager uses Monte Carlo to estimate the 99% one-day VaR of a portfolio using 1,000 simulated losses. She wants to compare this with …