FRM Part II · FRM Exam Part II · Backtesting VaR
A risk manager backtests a 95% one-day VaR model over 100 days and observes 9 exceptions. Using the normal approximation to the binomial with a 5% expected exception rate, what is the approximate z-statistic, (x - pT)/sqrt(p(1-p)T)?
The z-statistic is about 1.83. Expected exceptions are 5, the standard deviation is the square root of 4.75, about 2.18, and the excess of 4 exceptions divided by 2.18 gives roughly 1.83, which is below 1.96 and so not rejected at 5% two-sided.
- A1.83Correct
- B0.92
- C4.00
- D1.83 with the sign reversed
Explanation
Expected exceptions = 100 x 0.05 = 5. Standard deviation = sqrt(100 x 0.05 x 0.95) = sqrt(4.75) = 2.179. z = (9 - 5)/2.179 = 1.83. Using 4 without dividing by the standard deviation gives the 4.00 distractor, and 0.92 would come from dividing by 4.35 (using variance-like error).
Did you get it right without looking?
One question tells you little. A timed set on Backtesting VaR shows your real accuracy, how long you take and where you lose marks.
More Backtesting VaR questions
- A risk manager notes that a 99% VaR model had 3 exceptions in 250 days, all in consecutive days during one stress week. What is the most app…
- A risk manager backtests a 99% one-day VaR model over 250 days and wants to test both the correct number of exceptions and whether exception…
- A bank backtests its 95% one-day VaR over 500 days and records 35 exceptions. Using the normal approximation to the binomial, what is the z-…
- A bank's 99% one-day VaR model has 8 exceptions over 250 days in the yellow zone. Investigation shows 3 of them occurred because traders' po…
- A bank backtests its 99% one-day VaR over 500 days using hypothetical (clean) P&L, where positions are held fixed, and separately using actu…
- Over a backtest, a model produced 100 days after a non-exception day, of which 4 were exceptions, and 20 days after an exception day, of whi…