CS Professional · Arbitration, Mediation and Conciliation · Preparation and Execution of Arbitral Award
A three-member tribunal in a construction dispute between Varma Infra Ltd and Kaveri Steels Ltd finalises its award. Two arbitrators sign it. The third, who is seriously ill, cannot sign, and the award records this as the reason for the missing signature. Under Section 31, what is the position of the award?
The award is valid on this point. Where a tribunal has several arbitrators, signatures of a majority of all members are enough, provided the reason for any omitted signature is stated. Two of three signed and the illness is recorded, so the signature requirement is met.
- AThe award is invalid because every arbitrator must sign
- BThe award satisfies the signature requirement because a majority has signed and the reason for the omitted signature is statedCorrect
- CThe award is valid only if the parties consent in writing to the missing signature
- DThe award is valid only if the presiding arbitrator is one of the signatories and the court approves it
Explanation
Section 31(2) says that in a tribunal of more than one arbitrator, the signatures of a majority of all members suffice so long as the reason for any omitted signature is stated. Two of three is a majority and the reason is recorded. The option demanding all signatures ignores sub-section (2).
Did you get it right without looking?
One question tells you little. A timed set on Preparation and Execution of Arbitral Award shows your real accuracy, how long you take and where you lose marks.
More Preparation and Execution of Arbitral Award questions
- An arbitral tribunal sitting under an agreement fixing Pune as the place of arbitration under section 20 conducts hearings partly in Mumbai …
- Tribunal delivers an award to Raman Pharma and Delta Chemicals on 1 March. It decided claims A and B but did not deal with claim C, which wa…
- A tribunal seated at Hyderabad by agreement between Desai Motors Ltd and Khan Auto Parts passes an award that carries no signature date and …
- Mehta Exports Ltd and Sundaram Traders agreed in their arbitration clause that the tribunal need not give reasons for its award. The sole ar…
- In a domestic arbitration, pleadings under section 23(4) were completed on 1 April 2025. The parties consented to extend the time for the aw…
- A three-member tribunal sitting in Pune decides a dispute between Kaveri Textiles Ltd and Sahyadri Dyes Pvt Ltd. Two arbitrators sign the aw…