A trading desk repeatedly breaches its limits, and the CRO's escalation goes to the head of the desk's business line, who also determines the CRO's bonus. Which governance weakness is most directly illustrated, and what is the best remedy?
The weakness is compromised independence of the risk function, because the CRO's escalation and bonus depend on the business line being monitored. The remedy is to have the CRO report to the CEO or board risk committee, with compensation set independently, so breaches can be challenged without conflict.
- ACompromised independence of the risk function; the CRO should report to the CEO or board risk committee, with compensation set independently of the business lineCorrect
- BExcessive board involvement; the board should delegate limit setting entirely to desk heads
- CPoor data aggregation; the firm should purchase a faster risk engine
- DOver-reliance on VaR; the firm should abolish position limits
Explanation
When the CRO's pay and escalation path depend on the business line being monitored, the second line cannot challenge effectively. The remedy is a reporting line to the CEO and board risk committee, with independent compensation. Technology or abolishing limits does not address the conflict of interest.
Did you get it right without looking?
One question tells you little. A timed set on Enterprise Risk Management and Future Trends shows your real accuracy, how long you take and where you lose marks.
More Enterprise Risk Management and Future Trends questions
- A bank calculates economic capital for credit, market and operational risk separately and then simply adds the three figures to obtain total…
- A bank aggregates two risks with stand-alone economic capital of 60 and 80. Which correlation assumption makes the square-root aggregation f…
- A firm's board is deciding whether to enter a new overseas market. Management argues that the expected profit is attractive, but the downsid…
- In an enterprise risk management governance structure using the three lines model, which activity belongs to the second line?
- Which of the following is a recognized benefit of adopting ERM rather than managing risks in silos?
- A firm's two risk categories have stand-alone annual loss volatilities of USD 30 million (market risk) and USD 40 million (credit risk). Man…