Aarav Constructions engaged a specialist contractor for a special fabrication on Job 22. The cost of a drawing design prepared by an external consultant solely for Job 22 was Rs 45,000. How should this cost be classified in the cost sheet of Job 22?
The Rs 45,000 design fee is a direct expense and is charged directly to Job 22. It is incurred solely for that job, so it is traceable to the cost unit and is not apportioned as a factory, administration or selling overhead.
- ADirect expense, charged directly to Job 22Correct
- BFactory overhead, apportioned to all jobs
- CAdministration overhead
- DSelling and distribution overhead
Explanation
Direct expenses are expenses other than direct material and direct labour that are incurred specifically for a particular cost unit. A design made only for Job 22 is traceable to it, so it is charged directly. Apportioning it across all jobs would ignore the direct traceability.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- Which of the following is treated as an abnormal idle time cost and is therefore charged to the Costing Profit and Loss Account rather than …
- Under the Halsey premium plan with a 50% share to the worker, a worker is paid Rs 40 per hour. Standard time for a job is 50 hours and he fi…
- Ananya Textiles pays under the Halsey premium plan. Standard time for a job is 40 hours, actual time taken is 30 hours, and the hourly rate …
- Meenakshi Textiles pays under Rowan plan. The time rate is Rs 60 per hour, time allowed is 40 hours and time taken is 30 hours. What is the …
- Sharma Tools pays a worker under the Halsey premium plan. Standard time for a job is 40 hours, time taken is 30 hours, the wage rate is Rs. …
- Sharma Fabricators pays a worker under the Rowan plan. Standard time for a job is 20 hours, the hourly rate is Rs 80, and the worker finishe…