Under the Halsey premium plan with a 50% share to the worker, a worker is paid Rs 40 per hour. Standard time for a job is 50 hours and he finishes it in 40 hours. What is his total earning for the job?
The worker earns Rs 1,800. Time wages are 40 hours at Rs 40, which is Rs 1,600. He saves 10 hours, and under Halsey 50% of the saving at Rs 40 gives a bonus of Rs 200. Adding the two gives Rs 1,800.
- ARs 1,600
- BRs 1,800Correct
- CRs 2,000
- DRs 1,700
Explanation
Time wages = 40 x 40 = Rs 1,600. Time saved = 10 hours; bonus = 50% x 10 x 40 = Rs 200. Total = Rs 1,800. Rs 2,000 would pay the whole standard time (50 x 40), which is the Rowan-unrelated time-rate on standard hours, not Halsey.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- Which of the following is treated as an abnormal idle time cost and is therefore charged to the Costing Profit and Loss Account rather than …
- In a factory, the time spent by workers because of a power failure, for which they are paid wages but no production takes place, is called i…
- Ananya Textiles pays under the Halsey premium plan. Standard time for a job is 40 hours, actual time taken is 30 hours, and the hourly rate …
- Meenakshi Textiles pays under Rowan plan. The time rate is Rs 60 per hour, time allowed is 40 hours and time taken is 30 hours. What is the …
- Sharma Tools pays a worker under the Halsey premium plan. Standard time for a job is 40 hours, time taken is 30 hours, the wage rate is Rs. …
- Sharma Fabricators pays a worker under the Rowan plan. Standard time for a job is 20 hours, the hourly rate is Rs 80, and the worker finishe…