CS Professional · Arbitration, Mediation and Conciliation · Preparation and Execution of Arbitral Award
An award in favour of Desai Pharma was silent on the costs of the arbitration, and a question about those costs now arises between the parties. Which statement is correct under Section 39(4)?
Under Section 39(4), where a question arises about costs of the arbitration and the arbitral award contains no sufficient provision concerning them, the Court may make such orders respecting the costs as it thinks fit.
- AThe Court may make such orders as it thinks fit respecting the costs where the award contains no sufficient provision concerning themCorrect
- BThe Court must dismiss any dispute on costs because the award is final
- CThe arbitrator alone may reopen costs by a fresh award without any limit
- DThe costs must be borne equally by the parties by operation of law
Explanation
Section 39(4) empowers the Court to make such orders as it thinks fit respecting costs where any question arises and the award contains no sufficient provision on them. Equal sharing is not a rule under this sub-section, and the Court is not barred merely because the award is silent.
Did you get it right without looking?
One question tells you little. A timed set on Preparation and Execution of Arbitral Award shows your real accuracy, how long you take and where you lose marks.
More Preparation and Execution of Arbitral Award questions
- An arbitral tribunal sitting under an agreement fixing Pune as the place of arbitration under section 20 conducts hearings partly in Mumbai …
- Tribunal delivers an award to Raman Pharma and Delta Chemicals on 1 March. It decided claims A and B but did not deal with claim C, which wa…
- A tribunal seated at Hyderabad by agreement between Desai Motors Ltd and Khan Auto Parts passes an award that carries no signature date and …
- Mehta Exports Ltd and Sundaram Traders agreed in their arbitration clause that the tribunal need not give reasons for its award. The sole ar…
- In a domestic arbitration, pleadings under section 23(4) were completed on 1 April 2025. The parties consented to extend the time for the aw…
- A three-member tribunal sitting in Pune decides a dispute between Kaveri Textiles Ltd and Sahyadri Dyes Pvt Ltd. Two arbitrators sign the aw…