Anita, an internal auditor at Narmada Cements Ltd, reports that dispatch clearance is delayed. The draft states the problem but gives no cause, no effect on the company and no suggested action. Which set of elements would best make this finding complete and constructive?

A complete, constructive finding contains criteria, condition, cause, effect and a practical recommendation. This lets management understand what went wrong, why, and what it costs, and gives a workable route to correction, rather than merely naming people or stating an unexplained problem.

  1. AOnly the names of staff responsible for the delay
  2. BCriteria, condition, cause, effect and a practical recommendationCorrect
  3. CA summary of the previous year's findings without reference to current data
  4. DThe auditor's personal view on management's competence

Explanation

A complete finding sets out what should be (criteria), what was found (condition), why it happened (cause), the consequence (effect) and a workable recommendation. Naming staff or giving opinions on competence does not help management correct the process. Repeating old findings adds nothing for the current observation.