CS Professional · Internal and Forensic Audit · Reporting under Internal Audit
Anita, an internal auditor at Narmada Cements Ltd, reports that dispatch clearance is delayed. The draft states the problem but gives no cause, no effect on the company and no suggested action. Which set of elements would best make this finding complete and constructive?
A complete, constructive finding contains criteria, condition, cause, effect and a practical recommendation. This lets management understand what went wrong, why, and what it costs, and gives a workable route to correction, rather than merely naming people or stating an unexplained problem.
- AOnly the names of staff responsible for the delay
- BCriteria, condition, cause, effect and a practical recommendationCorrect
- CA summary of the previous year's findings without reference to current data
- DThe auditor's personal view on management's competence
Explanation
A complete finding sets out what should be (criteria), what was found (condition), why it happened (cause), the consequence (effect) and a workable recommendation. Naming staff or giving opinions on competence does not help management correct the process. Repeating old findings adds nothing for the current observation.
Did you get it right without looking?
One question tells you little. A timed set on Reporting under Internal Audit shows your real accuracy, how long you take and where you lose marks.
More Reporting under Internal Audit questions
- Orion Steels Ltd's internal audit report on inventory is well written, but the statutory auditor wants to judge the quality of the work behi…
- Kaveri Textiles Ltd's internal auditor completes a review of the procurement cycle. The CFO asks why a written report is needed when the fin…
- Meera, the head of internal audit at Kaveri Textiles Ltd, is finalising a report on the procurement cycle. Which combination of content best…
- The internal auditor of Gupta Steels Ltd. found that the plant head's relative was awarded a contract without tendering. The plant head requ…
- During a review of a manufacturing firm's stores function, an internal auditor of Sharma Textiles Ltd. drafts a report that uses long techni…
- During coordination, Meera, an internal auditor at Bharat Logistics Ltd, tells the external auditor that she suspects a purchase manager has…