CMA Final · Strategic Cost Management · Assignment
Arjun Fabricators must assign three jobs (A, B, C) to three machines (M1, M2, M3), one job per machine. Processing costs in Rs thousand are: A: 9, 11, 14; B: 6, 15, 13; C: 12, 13, 6 (for M1, M2, M3 respectively). What is the minimum total cost?
The minimum total cost is Rs 23 thousand, obtained by assigning job A to M2, job B to M1 and job C to M3. Every other one-to-one assignment costs more, for example the diagonal pairing costs Rs 30 thousand.
- ARs 23 thousandCorrect
- BRs 30 thousand
- CRs 26 thousand
- DRs 33 thousand
Explanation
Check all six assignments: 30, 35, 23, 36, 33, 41. The least is A-M2, B-M1, C-M3 = 11+6+6 = 23. Rs 30 comes from the diagonal assignment A-M1, B-M2, C-M3, which is not the cheapest.
Did you get it right without looking?
One question tells you little. A timed set on Assignment shows your real accuracy, how long you take and where you lose marks.
More Assignment questions
- A firm assigns three salespersons P, Q, R to three territories, one each, to maximise profit. Monthly profit in Rs. thousand for territories…
- Three workers A, B and C are to be assigned one each to jobs 1, 2 and 3. The cost in ₹ thousand is: A: 8, 6, 10; B: 9, 12, 7; C: 11, 9, 8 (f…
- Three operators W1, W2 and W3 are available for four jobs J1 to J4; each operator can do only one job and one job will remain undone. Costs …
- Three technicians A, B and C are to be assigned one each to three jobs J1, J2 and J3. The cost (₹ '000) is: A: 9, 11, 14; B: 12, 7, 10; C: 8…
- Three workers W1, W2, W3 are available for four jobs J1 to J4, and each worker can take at most one job; one job stays unassigned. Costs (Rs…
- A firm assigns salesmen P, Q, R one each to territories X, Y, Z to maximise monthly profit (Rs thousand). Profits for X, Y, Z: P: 40, 35, 25…