ACCA Strategic Professional · Strategic Business Reporting (International) · Provisions, contingencies and events after the reporting period
At 31 December 20X5, Kestrel Co has a legal case brought against it by a customer. Its lawyers advise that it is more likely than not that Kestrel will lose and that a payment of $2 million will be required. Kestrel's financial statements are authorised in March 20X6. What is the correct treatment at 31 December 20X5 under IAS 37?
Kestrel should recognise a provision of $2 million. The past event gives a present obligation, an outflow is probable because loss is more likely than not, and the amount can be estimated reliably, so all IAS 37 recognition criteria are met.
- ADisclose a contingent liability only, because the outcome is not certain
- BRecognise a provision of $2 millionCorrect
- CRecognise a contingent asset of $2 million
- DMake no recognition or disclosure, because the case is not yet settled
Explanation
A provision is recognised when there is a present obligation from a past event, an outflow is probable (more likely than not), and a reliable estimate can be made. The lawyers' advice satisfies all three conditions. Disclosure only would apply if the outflow were merely possible.
Did you get it right without looking?
One question tells you little. A timed set on Provisions, contingencies and events after the reporting period shows your real accuracy, how long you take and where you lose marks.
More Provisions, contingencies and events after the reporting period questions
- Zeta plc sells equipment with a one-year warranty. At the reporting date, past sales have created a warranty obligation. Based on experience…
- Tandor Co operates an offshore platform and must remove it at the end of its 10-year life. It is obliged to do so because of installing it. …
- Zenith Ltd is defending a lawsuit claiming damages of $2 million for alleged product defects. Its legal advisers believe it is possible, but…
- Halden Group must restore a mine site. The restoration obligation of $5m (present value) arose on extraction. At the next year end, a revise…
- Sigma Ltd's finance director asks the financial controller to omit disclosure of a material contingent liability for an environmental claim,…
- Sigma plc is finalising consolidated statements for the year ended 31 December 20X5, to be authorised on 28 March 20X6. On 10 February 20X6 …