ACCA Strategic Professional · Advanced Financial Management · Application of option pricing theory in investment decisions
Baltic Ltd has a project with a static NPV of -$1.5m. It holds an option to delay the investment by one year. Using Black-Scholes, the option is valued as a call with these results: N(d1)=0.65, N(d2)=0.50, PV of project cash inflows $20m, PV of the exercise price (investment outlay) $19.0m. What is the value of the delay option, and what is the expanded NPV of the project if the option is valued as N(d1) x Pa - N(d2) x PV(Pe)?
The option is worth $3.5m, from 0.65 x 20 minus 0.50 x 19. Adding this to the static NPV of -$1.5m gives an expanded NPV of $2.0m, so the project becomes worthwhile once the flexibility to delay is valued.
- AOption value $3.5m; expanded NPV $2.0mCorrect
- BOption value $3.5m; expanded NPV -$1.5m
- COption value $13.0m; expanded NPV $11.5m
- DOption value $2.0m; expanded NPV $0.5m
Explanation
Option value = 0.65 x 20 - 0.50 x 19 = 13.0 - 9.5 = 3.5m. Expanded NPV = -1.5 + 3.5 = $2.0m. Ignoring the static NPV gives 3.5m only, and omitting N(d2) gives 13.0m, both wrong.
Did you get it right without looking?
One question tells you little. A timed set on Application of option pricing theory in investment decisions shows your real accuracy, how long you take and where you lose marks.
More Application of option pricing theory in investment decisions questions
- Bramwell plc is valuing a real option to delay a project. It has no traded shares on the project itself, so it needs an estimate of volatili…
- Dunmore Co values a real option on a new project using the equity share price volatility of a highly geared listed comparator in the same in…
- Arden Ltd shares trade at $100. A one-year European call (exercise $100) is valued at $12 and a one-year European put (exercise $100) at $7.…
- Which statement about the effect of an expected dividend payment before expiry on the value of European options on a share is correct, all e…
- A European call option on a non-dividend-paying share has an exercise price of $62 and expires in six months. The share price is $60, the co…
- Zentra plc is valuing an option to expand a project using the Black-Scholes model. Which input for the underlying asset is typically the har…