ACCA Strategic Professional · Strategic Business Leader · Leading and managing projects
Bramwell Co is planning a product launch project. The activities are: A (3 weeks, no predecessor), B (5 weeks, after A), C (2 weeks, after A), D (4 weeks, after B and C). A manager says the project can finish in 9 weeks by running B and C in parallel. What does network analysis indicate, and what is the float on activity C?
The minimum duration is 12 weeks, set by the critical path A-B-D (3+5+4). Activity C lies on a path of only 9 weeks, so it has 3 weeks of float. Running B and C in parallel does not shorten the project below the longest path.
- AMinimum duration 12 weeks; float on C is 3 weeksCorrect
- BMinimum duration 12 weeks; float on C is 2 weeks
- CMinimum duration 9 weeks; float on C is 3 weeks
- DMinimum duration 14 weeks; float on C is zero
Explanation
Critical path is A-B-D = 3+5+4 = 12 weeks. Path A-C-D = 3+2+4 = 9 weeks, so C has float of 12-9 = 3 weeks. The 9-week claim wrongly ignores that D cannot start until B (the longer branch) finishes. A 14-week figure wrongly adds B and C as if sequential, with no parallel running.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Baraka Telecom is building a network upgrade. A key risk is that the sole supplier of a specialised component may fail to deliver on time. T…
- Orlin Health is running a project through defined phases: concept, definition, implementation, handover and closure. The steering group insi…
- Brightwell Council is running a major IT project. The project manager is told by the sponsor that a community group, which has no formal pow…
- Zentra Foods, a mid-sized manufacturer, is considering a new automated packing line. The board has asked the operations director to produce …
- Zephyr Logistics is launching a new warehouse management system. Midway through the project, several departmental heads each ask for additio…
- Halden Logistics completed a new warehouse management system on the agreed date and within the approved budget, and it met every technical s…