Brenmoor Ltd is considering a project with three possible outcomes: a profit of $400,000 with probability 0.5, a profit of $100,000 with probability 0.3, and a loss of $200,000 with probability 0.2. What is the expected value of the project, and what does it fail to show?

The expected value is $190,000, calculated as 200,000 plus 30,000 less 40,000. It is a probability-weighted average, so it does not reveal the spread of outcomes or the risk of loss, such as the 20% chance of losing $200,000.

  1. A$190,000; it does not show the spread or variability of outcomesCorrect
  2. B$300,000; it does not show the average outcome
  3. C$190,000; it shows the worst-case loss
  4. D$100,000; it does not show the spread or variability of outcomes

Explanation

EV = 0.5 x 400,000 + 0.3 x 100,000 + 0.2 x (-200,000) = 200,000 + 30,000 - 40,000 = $190,000. Expected value is an average and hides dispersion, such as the 20% chance of a loss. The $300,000 option wrongly ignores the probabilities of the loss and treats the outcomes as simple highs.