ACCA Strategic Professional · Advanced Financial Management · Impact of financing on investment decisions and adjusted present values
Brennan Co finances a project with $4 million of five-year, interest-only debt at 5% before tax. The debt is repaid at the end of year 5 and the tax rate is 30%. Tax shields arise at the end of each year and are discounted at the pre-tax cost of debt. The five-year annuity factor at 5% is 4.329 and at 10% is 3.791. What is the PV of the tax shield?
The PV of the tax shield is $259,740. The annual shield is $4m × 5% × 30%, which is $60,000, and this is discounted for five years using the 4.329 annuity factor at the 5% pre-tax cost of debt.
- A$259,740Correct
- B$300,000
- C$227,460
- D$865,800
Explanation
Annual shield = $4m × 5% × 30% = $60,000. PV = $60,000 × 4.329 = $259,740. $300,000 is undiscounted. $227,460 wrongly uses a 10% factor. $865,800 ignores the tax rate (uses $200,000 of interest).
Did you get it right without looking?
One question tells you little. A timed set on Impact of financing on investment decisions and adjusted present values shows your real accuracy, how long you take and where you lose marks.
More Impact of financing on investment decisions and adjusted present values questions
- Nyala Ltd is an all-equity project-financed company with an equity beta of 1.20. Risk-free rate is 4% and market return is 9%. Under the APV…
- A company uses APV to appraise a project financed by newly issued debt. Which of the following is a financing side effect that should be inc…
- A company with a constant debt-to-equity ratio of 1:2 (by market value) has a geared cost of equity of 12%. Its pre-tax cost of debt is 5% a…
- In the adjusted present value (APV) method, at which rate are the base-case after-tax operating cash flows of a project normally discounted?
- Bexley Co is appraising a project costing $10m now. It will give after-tax operating cash flows of $3.2m a year for 5 years. The ungeared co…
- Orla plc is appraising a project costing $4m. The base-case NPV, discounted at the ungeared cost of equity of 8%, is $300,000. The project i…