ACCA Strategic Professional · Advanced Performance Management · Budgetary planning and control
Brevik Ltd uses a 90% learning curve for a new product. The first unit requires 100 labour hours and the cumulative average time model applies. Labour costs 20 per hour. What is the budgeted labour cost for producing the first 4 units in total?
The budgeted labour cost is 6,480. Under a 90% curve, the cumulative average time after two doublings is 81 hours per unit, so four units need 324 hours. At 20 per hour that equals 6,480.
- A6,480Correct
- B8,000
- C7,200
- D7,290
Explanation
With cumulative average time, doubling output from 1 to 2 gives an average of 90 hours, and doubling to 4 gives 81 hours average. Total hours = 4 x 81 = 324. Cost = 324 x 20 = 6,480. Using 100 hours per unit gives 8,000, which ignores learning, and 7,200 uses only one doubling.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary planning and control shows your real accuracy, how long you take and where you lose marks.
More Budgetary planning and control questions
- At Kellerman Co, sales managers know that bonuses are paid when actual sales exceed budget. During budget setting they deliberately understa…
- Harlow Components uses an annual fixed budget agreed in November. By June, market conditions have changed sharply, yet managers are still ju…
- Brandt Plc is considering how difficult to make budget targets. Research on motivation suggests which targets are most likely to maximise pe…
- Orlin Group uses a budget-constrained evaluation style: managers are judged mainly on meeting the annual cost budget, with severe consequenc…
- Norvik Services is considering moving to a Beyond Budgeting model. Which of the following changes is most consistent with that philosophy?
- Orion Ltd budgeted 2,000 labour hours at $15 to make 1,000 units. Actual output was 1,100 units using 2,300 hours, paid at $14.50 per hour. …