ACCA Strategic Professional · Advanced Performance Management · Budgetary planning and control
Harlow Components uses an annual fixed budget agreed in November. By June, market conditions have changed sharply, yet managers are still judged on variances against the original budget. Which Beyond Budgeting principle most directly addresses this weakness?
Beyond Budgeting deals with outdated fixed targets by using relative targets and rolling forecasts, so managers are judged against current conditions rather than assumptions made months earlier. More detail, central approval or a longer fixed period would not fix the lack of responsiveness.
- AReplacing fixed annual targets with relative targets and rolling forecasts that reflect current conditionsCorrect
- BIncreasing the number of budget line items so variances are analysed in more detail
- CMoving budget approval to a single senior committee to improve consistency
- DExtending the budget period to three years to reduce the frequency of negotiation
Explanation
Beyond Budgeting replaces fixed annual targets with relative, stretch targets and rolling forecasts so performance is judged against the current environment. More detail or centralised approval keeps the fixed-contract problem. A longer fixed period makes the targets even less relevant as conditions change.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary planning and control shows your real accuracy, how long you take and where you lose marks.
More Budgetary planning and control questions
- Tessen Group operates in a volatile sector. It is replacing its annual budget with a Beyond Budgeting model. Senior managers are concerned t…
- A divisional manager receives a monthly report showing a large adverse materials price variance caused by a supplier price rise imposed by h…
- Dalton Retail's budgeted sales were 5,000 units at $20, with a standard contribution of $8 per unit. Actual sales were 4,600 units at $21. V…
- Tarn Engineering evaluates plant managers using a budget-constrained style, so a manager is judged solely on meeting the budgeted cost every…
- Marlow Ltd budgeted 8,000 units with variable overhead of $5 per unit and fixed overhead of $40,000. Actual output was 9,000 units and actua…
- Quorra Software develops products in a fast-changing, innovative sector. Its CEO is considering replacing the traditional annual budget with…