Brindle Ltd has a project requiring an initial outlay of $10 million, funded by a $4 million debt. The debt is fixed at $4 million permanently, with pre-tax interest at 6% and tax at 25%. Interest is deductible, and the tax shield is discounted at the 6% cost of debt. What is the present value of the tax shield?
The present value of the tax shield is $1.00 million. With permanent debt discounted at the cost of debt, the value is simply debt multiplied by the tax rate, $4 million times 25%, since the interest rate cancels out.
- A$1.00 millionCorrect
- B$0.24 million
- C$4.00 million
- D$1.50 million
Explanation
For permanent debt, PV of tax shield = debt x tax rate = 4 x 25% = $1.00 million. Check: annual shield = 4 x 6% x 25% = 0.06, divided by 6% = 1.00. Using 10 million of debt would give 2.5; $0.24m is just one year's interest.
Did you get it right without looking?
One question tells you little. A timed set on Discounted cash flow techniques shows your real accuracy, how long you take and where you lose marks.
More Discounted cash flow techniques questions
- Which statement about using CAPM-based project discount rates is correct?
- A company faces capital constraints at time 0 and again at time 1, and its projects are divisible. Why is ranking projects by a single profi…
- A company has a one-period capital constraint, and projects X, Y and Z are divisible. A linear programming formulation gives a shadow price …
- Varley plc is appraising a project with an initial outlay of $200,000 now and a single net cash inflow of $242,000 at the end of year 2. The…
- A proxy company has an equity beta of 1.20, a debt beta of zero, and a market value gearing of debt:equity of 1:3. Tax is 25%. Using the for…
- A company is appraising a project using a nominal (money) cost of capital. Which treatment of cash flows is consistent?