Budgeted output was 1,000 units with a budgeted variable cost of $40,000 and a budgeted fixed cost of $25,000. Actual output was 1,200 units. What is the flexed budget total cost for actual output?

The flexed budget total cost is $73,000. Variable cost per unit is $40, so 1,200 units give $48,000, while the fixed cost of $25,000 does not change with output. Adding them gives $73,000.

  1. A$73,000Correct
  2. B$78,000
  3. C$65,000
  4. D$48,000

Explanation

Variable cost per unit = $40. Flexed variable cost = 1,200 x 40 = $48,000. Fixed cost stays at $25,000. Total = $73,000. The $78,000 option wrongly flexes fixed cost too (25,000 x 1.2 = 30,000, plus 48,000).