ACCA Applied Knowledge · Management Accounting · Standard costing system
Which of the following is a primary purpose of operating a standard costing system in a manufacturing company?
The primary purpose of standard costing is to provide a predetermined benchmark so that actual costs can be compared with it. The resulting variances are investigated under management by exception. It does not measure exact actual unit cost, replace budgets, or value inventory at selling price.
- ATo value inventory at the highest possible selling price
- BTo provide a benchmark against which actual costs can be compared so that variances can be investigatedCorrect
- CTo eliminate the need for a budget
- DTo calculate the exact actual cost of each unit produced
Explanation
A standard cost is a predetermined unit cost. Its main uses are to act as a benchmark for control, to highlight variances for management by exception, and to simplify inventory valuation and costing. It does not give actual cost, it does not replace budgets, and inventory is not valued at selling price.
Did you get it right without looking?
One question tells you little. A timed set on Standard costing system shows your real accuracy, how long you take and where you lose marks.
More Standard costing system questions
- Which of the following is the most appropriate description of a standard cost card for a product?
- A company sets its standard cost card for Product Z at 4 kg of material at $5 per kg, 2 hours of labour at $12 per hour, and variable overhe…
- A standard cost card for Product Q shows variable overhead of $4 per labour hour and a standard time of 2.5 hours per unit. The standard sel…
- A company's standard labour rate was $14 per hour. Because of a shortage of skilled workers, it used more highly skilled staff paid $16 per …
- Which type of standard assumes ideal operating conditions, with no allowance for wastage, idle time or machine breakdowns?
- Brill Co has a standard labour rate of $12 per hour. Actual output of 2,000 units took 4,300 hours and the total labour cost was $53,750. Th…