ACCA Applied Knowledge · Management Accounting · Cost reductions and value enhancement
Budgeted output was 10,000 units with a standard labour cost of $12 per unit. Actual output was 11,000 units and actual labour cost was $135,000. A cost reduction programme during the year permanently lowered the standard labour cost to $11 per unit, but reports still used the original standard. What is the labour cost variance based on the ORIGINAL standard, and what would it be against the revised standard?
Against the original standard the variance is $3,000 adverse, since flexed standard cost is $132,000 against actual of $135,000. Against the revised standard of $11 per unit, flexed cost is $121,000, so the variance is $14,000 adverse.
- A$3,000 adverse against the original; $14,000 adverse against the revisedCorrect
- B$3,000 adverse against the original; $16,000 adverse against the revised
- C$15,000 adverse against the original; $14,000 adverse against the revised
- D$3,000 adverse against the original; $14,000 favourable against the revised
Explanation
Original flexed standard cost = 11,000 × $12 = $132,000. Actual $135,000 gives $3,000 adverse. Revised standard = 11,000 × $11 = $121,000. Actual $135,000 gives $14,000 adverse. The second option wrongly computes the revised standard cost as $119,000, and the others misuse the base or sign.
Did you get it right without looking?
One question tells you little. A timed set on Cost reductions and value enhancement shows your real accuracy, how long you take and where you lose marks.
More Cost reductions and value enhancement questions
- A product has a current cost of $50 per unit. A Kaizen programme requires a 2% reduction in the previous month's cost each month, starting w…
- Which of the following is a risk of pursuing cost reduction through a lower-quality material?
- Which of the following is a typical feature of target costing, as opposed to Kaizen costing?
- Which of the following is a typical step or feature of value engineering rather than a limitation of it?
- Dunmore Co uses target costing for a product with a target selling price of $50 and a required margin of 30% on selling price. Variable cost…
- A company is value engineering a product. Current unit cost is $80 and the target cost for a required margin is $68. Redesign of components …