ACCA Applied Knowledge · Management Accounting · Budgetary control and reporting
Budgeted production was 5,000 units with variable costs of $4 per unit and fixed costs of $18,000. Actual production was 6,000 units, with actual total costs of $43,000. What is the total cost variance against the flexed budget?
The flexed budget cost for 6,000 units is $24,000 variable plus $18,000 fixed, totalling $42,000. Actual cost was $43,000, so costs were $1,000 over the flexed budget, an adverse variance. Fixed costs are not flexed with output.
- A$1,000 favourable
- B$1,000 adverseCorrect
- C$7,000 adverse
- D$6,000 adverse
Explanation
Flexed budget cost = 6,000 x $4 = $24,000 + $18,000 fixed = $42,000. Actual cost is $43,000, so the variance is $1,000 adverse. Comparing with the original budget of $38,000 gives $5,000 adverse, which is misleading, and the $7,000 and $6,000 options come from other incorrect bases.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary control and reporting shows your real accuracy, how long you take and where you lose marks.
More Budgetary control and reporting questions
- Which one of the following is a feature of a budget report designed on the principle of responsibility accounting?
- Which of the following best describes a controllable cost in the context of budgetary control reporting?
- Budgeted production at Orion Ltd was 10,000 units, with fixed overheads of $80,000 and variable overheads of $3 per unit. Actual production …
- A department's original budget was 2,000 labour hours at $15 per hour. Actual output required 2,300 hours in the flexed budget, and actual l…
- A company's monthly budgetary control report compares actual results with the original fixed budget. Actual output was 12,000 units against …
- A company's budget for a period was 5,000 units of output at a total cost of $60,000, of which $20,000 is fixed. Actual output was 5,500 uni…