ACCA Applied Skills · Performance Management · Throughput accounting
Dalton Co has a bottleneck machine. Throughput per machine hour is $20 for product S and $14 for product T. Management proposes to make more of T because it has higher demand. Which is the best advice under throughput accounting?
Product S should be made first because it earns $20 of throughput per bottleneck hour compared with $14 for T. Throughput accounting ranks products by return per unit of the constraining resource, not by demand level or labour cost.
- AMake T first, because demand is higher
- BMake S first, because it earns more throughput per bottleneck hourCorrect
- CMake both in proportion to demand
- DMake T first, because it has lower labour cost
Explanation
Under throughput accounting the bottleneck should be exploited by producing in order of throughput per bottleneck hour. S earns $20 against $14 for T, so S should be made first, up to demand. Demand and labour cost do not determine the ranking.
Did you get it right without looking?
One question tells you little. A timed set on Throughput accounting shows your real accuracy, how long you take and where you lose marks.
More Throughput accounting questions
- Trent Ltd uses throughput accounting. Product Q sells for $50 per unit, with direct material cost of $18 per unit, direct labour of $10 per …
- Marlow Co has a product with a selling price of $90 and material cost of $30 per unit. Each unit needs 0.5 hours on the bottleneck. Total fa…
- Which of the following best describes the objective of throughput accounting?
- Under throughput accounting, which of the following is treated as the only cost that is variable in the short term when calculating throughp…
- Under the Theory of Constraints, which step comes immediately after identifying the system's bottleneck resource?
- Which statement about a non-bottleneck resource in a throughput accounting system is correct?