Under the Theory of Constraints, which step comes immediately after identifying the system's bottleneck resource?
After identifying the bottleneck, the next step is to exploit it, meaning it should be kept fully working and used only on output that is needed. Subordinating other resources and elevating capacity follow later in the sequence.
- AExploit the bottleneck by making sure it is never idle and produces only what is neededCorrect
- BElevate the bottleneck by buying additional capacity
- CSubordinate all other resources to the bottleneck
- DIncrease the bottleneck's capacity until a new constraint emerges
Explanation
The five focusing steps are: identify the constraint, exploit it, subordinate everything else to it, elevate it, then repeat. Subordination comes after exploitation, and elevation (adding capacity) comes only once the existing capacity has been fully exploited.
Did you get it right without looking?
One question tells you little. A timed set on Throughput accounting shows your real accuracy, how long you take and where you lose marks.
More Throughput accounting questions
- Under throughput accounting, which of the following is treated as the only cost that is variable in the short term when calculating throughp…
- Which statement about a non-bottleneck resource in a throughput accounting system is correct?
- Kestrel Ltd has 900 bottleneck hours available. Product P: throughput $48 per unit, 4 hours per unit, demand 150 units. Product R: throughpu…
- Marlow Co makes products A and B using a single bottleneck machine. A: selling price $90, materials $30, machine time 4 minutes. B: selling …
- Dalton Co has a bottleneck machine. Throughput per machine hour is $20 for product S and $14 for product T. Management proposes to make more…
- Trent Ltd uses throughput accounting. Product Q sells for $50 per unit, with direct material cost of $18 per unit, direct labour of $10 per …