ACCA Strategic Professional · Strategic Business Leader · Identification, assessment and measurement of risk
Delmar Retail estimates that a data breach has a 5% annual probability and would cost $2 million. A fire at a warehouse has a 20% annual probability and would cost $400,000. A board member proposes ranking the risks solely by expected value. What is the key limitation of this approach as applied to these risks?
Expected values are $100,000 for the breach and $80,000 for the fire, but expected value averages outcomes and hides that the breach would be a single large loss. Boards should also consider the size of impact, particularly where one event could threaten the organisation's survival.
- AExpected value of the breach is $100,000 against $80,000 for the fire, but averaging hides the catastrophic size of the single breach loss, so impact should also be considered separatelyCorrect
- BExpected value of the fire is $400,000 so it must be ranked first
- CExpected value ignores probability, so it cannot be calculated
- DExpected value shows the breach is less important because its probability is lower
Explanation
Breach: 5% x 2,000,000 = 100,000. Fire: 20% x 400,000 = 80,000. Expected values are similar, but the breach could be a single large loss that threatens survival; expected value averages this out, so impact needs separate attention.
Did you get it right without looking?
One question tells you little. A timed set on Identification, assessment and measurement of risk shows your real accuracy, how long you take and where you lose marks.
More Identification, assessment and measurement of risk questions
- Brightwave Energy rates a project risk as medium likelihood and very high impact. Its board has a low risk appetite and a stated risk tolera…
- Orlando Retail's risk register rates a data breach as low likelihood but very high impact, because customer records would be exposed and reg…
- Harbour Freight plc, a logistics group, has plotted its risks on a likelihood-impact matrix. A cyber-attack that would shut down its booking…
- Orlan Mining plc faces a political risk in a country where it operates: nationalisation of its mine. Likelihood is judged low, but impact wo…
- Orlo Pharma's board is risk neutral at corporate level and evaluates projects by expected value. Project A yields 10m with certainty. Projec…
- Kallis Energy's board wants to estimate the maximum loss on its commodity portfolio that would not be exceeded on 99% of days over a one-day…