Estrel Co uses a standard absorption costing system with fixed overheads absorbed at $8 per labour hour. Budgeted fixed overheads were $96,000 based on 12,000 hours. Actual output took 11,000 hours at standard, actual hours worked were 11,400, and actual fixed overheads were $98,500. What is the fixed overhead expenditure variance?
The fixed overhead expenditure variance is $2,500 adverse. It compares the budgeted fixed overhead of $96,000 with the actual spend of $98,500, so the company spent $2,500 more than planned, regardless of output or hours worked.
- A$2,500 adverseCorrect
- B$2,500 favourable
- C$8,500 adverse
- D$10,500 adverse
Explanation
Expenditure variance = budgeted fixed overhead $96,000 − actual $98,500 = $2,500 adverse. Option 3 mixes in the volume variance. Hours worked do not affect the expenditure variance.
Did you get it right without looking?
One question tells you little. A timed set on Monitoring performance and reporting shows your real accuracy, how long you take and where you lose marks.
More Monitoring performance and reporting questions
- Zeta Co budgeted to produce 5,000 units using 2 kg of material per unit at a standard price of $4 per kg. Actual output was 5,200 units, usi…
- A company reports sales of $840,000, cost of sales of $504,000 and operating expenses of $210,000. What is its operating profit margin?
- Harlow Ltd's standard cost for one unit of Product P is 4 kg of material at $5 per kg. In March, 1,000 units were produced and 4,200 kg of m…
- Orla Ltd budgeted sales of 1,000 units at a standard contribution of $12 per unit. Actual sales were 1,100 units. Orla uses marginal costing…
- Which of the following is the best reason for restricting a manager's performance report to controllable items only?
- Which of the following is a non-financial performance measure most appropriate for assessing the quality of a call centre's service?