For a raw material, Bharat Fabrics records usage of 60 to 120 units per day, with a normal usage of 90 units per day. Lead time ranges from 8 to 12 days, and the average is 10 days. What is the reorder level?
The reorder level is 1,440 units, found by multiplying maximum daily consumption of 120 units by maximum lead time of 12 days. The other figures mix normal or average values and so do not follow the standard reorder level formula.
- A900 units
- B1,080 units
- C1,200 units
- D1,440 unitsCorrect
Explanation
Reorder level = maximum consumption x maximum lead time = 120 x 12 = 1,440 units. 900 uses normal usage and average lead time, 1,200 uses maximum usage with average lead time, and 1,080 uses normal usage with maximum lead time; none of these is the formula.
Did you get it right without looking?
One question tells you little. A timed set on Management of Inventory shows your real accuracy, how long you take and where you lose marks.
More Management of Inventory questions
- Annual demand for an item is 3,600 units. Daily usage is uniform over a 360-day year. Lead time is normally 10 days but could be as long as …
- In inventory management, the ABC system of control classifies items mainly on which basis?
- In the ABC (Always Better Control) analysis of inventory, which statement correctly describes 'A' category items?
- Which of the following best describes 'carrying cost' in the context of inventory management?
- Mehta Auto Ltd uses 600 units of a part per week (52 weeks a year). Lead time is normally 4 weeks but can be as long as 6 weeks; the minimum…
- Anand Steels uses 100 units of a material daily. Lead time varies from 8 to 12 days, with a normal lead time of 10 days. What is the reorder…