CA Intermediate · Financial Management and Strategic Management · Management of Inventory
Mehta Auto Ltd uses 600 units of a part per week (52 weeks a year). Lead time is normally 4 weeks but can be as long as 6 weeks; the minimum consumption is 400 units per week. Maximum consumption is 800 units per week. What is the reorder level using maximum consumption and maximum lead time?
The reorder level is 4,800 units, found by multiplying maximum weekly consumption of 800 units by maximum lead time of 6 weeks. Options using average usage or normal lead time understate the level needed to avoid a stockout.
- A2,400 units
- B3,600 units
- C4,800 unitsCorrect
- D3,200 units
Explanation
Reorder level = maximum consumption x maximum lead time = 800 x 6 = 4,800 units. Using average consumption and normal lead time gives 600 x 4 = 2,400, which is the wrong base. Using 600 x 6 = 3,600 mixes average usage with maximum lead time; 800 x 4 = 3,200 mixes maximum usage with normal lead time.
Did you get it right without looking?
One question tells you little. A timed set on Management of Inventory shows your real accuracy, how long you take and where you lose marks.
More Management of Inventory questions
- Which of the following is a carrying (holding) cost of inventory, as distinct from an ordering cost?
- Sundaram Fasteners Ltd uses 18,000 units of a component a year. Ordering cost is Rs 250 per order and carrying cost is Rs 5 per unit per yea…
- Annual demand for a component at Sundaram Engineering is 7,200 units. Ordering cost is Rs 250 per order and carrying cost is Rs 10 per unit …
- In ABC analysis of inventory, which treatment is most appropriate for Category A items?
- Anand Auto Ltd has a lead time of 10 days, maximum daily usage of 60 units and normal daily usage of 50 units. The maximum lead time is 14 d…
- Which of the following best describes the Just-in-Time (JIT) approach to inventory management?