CA Intermediate · Advanced Accounting · AS 7 Construction Contracts

Ganga Infra Ltd entered into a fixed price contract to build a flyover for Rs 8,00,000 thousand... Correction: Ganga Infra Ltd entered into a fixed price contract for Rs 80 lakh to build a culvert. At the year-end, contract costs incurred to date were Rs 30 lakh and estimated further costs to complete were Rs 30 lakh. Using the cost-to-cost method under AS 7, what revenue is recognised for the year (first year of the contract)?

Revenue is Rs 40 lakh. Total estimated cost is Rs 60 lakh, so the stage of completion is 30/60, or 50 percent. Applying this to the fixed contract price of Rs 80 lakh gives Rs 40 lakh of revenue for the year under the percentage of completion method.

  1. ARs 30 lakh
  2. BRs 40 lakhCorrect
  3. CRs 50 lakh
  4. DRs 80 lakh

Explanation

Total estimated cost = 30 + 30 = Rs 60 lakh. Percentage complete = 30/60 = 50%. Revenue = 50% of Rs 80 lakh = Rs 40 lakh. Rs 30 lakh is wrong because it simply equates revenue to cost incurred, which is the zero-profit approach used only when the outcome cannot be estimated reliably.

Did you get it right without looking?

One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.

More AS 7 Construction Contracts questions