CA Intermediate · Advanced Accounting · AS 7 Construction Contracts
Ganga Infra Ltd is building a flyover for a state road authority under a fixed price contract and is compiling the contract costs under AS 7. Which one of the following items will NOT be included in contract costs for the flyover?
Selling costs are excluded from contract costs under AS 7. Site plant depreciation, design costs directly related to the contract, and contract insurance are all costs that relate directly to the contract or can be allocated to it. Selling costs do not qualify because they are not attributable to contract activity.
- ADepreciation of a crane used exclusively at the flyover site
- BCost of design and technical assistance directly related to the flyover
- CSelling costs incurred by Ganga Infra Ltd to market its construction services generallyCorrect
- DInsurance premium paid on the flyover site works
Explanation
AS 7 includes costs that relate directly to the specific contract, such as site plant depreciation, design and technical assistance directly related to the contract, and contract insurance. Selling costs are not attributable to contract activity or allocable to the contract, so they are excluded. Hence the selling costs are the only item left out of the contract costs.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- Himalaya Projects Ltd has a fixed price contract of ₹500 lakh. At the end of the first year, costs incurred are ₹300 lakh and the estimated …
- Meridian Infra Ltd is building a flyover for a state government under a construction contract. Its accountant is listing the costs for the c…
- Ganga Builders Ltd started a fixed price contract of ₹600 lakh during the current year. Costs incurred to date are ₹420 lakh and estimated f…
- Sagar Infra Ltd undertook a fixed price contract for Rs 80 lakh to build a warehouse for Kiran Traders. Costs incurred to date: Rs 30 lakh; …
- Shivalik Constructions Ltd has a fixed price contract of ₹1,000 lakh. At the year end, costs incurred to date are ₹480 lakh, which include ₹…
- Navkar Infra Ltd is building a bridge under a fixed price contract. The contract does not specify that general administration costs are reim…