CA Intermediate · Cost and Management Accounting · Unit & Batch Costing
Gupta Bottlers produces a product in batches of 5,000 units. Per batch, set-up cost is ₹2,500, material is ₹30,000, and labour is ₹20,000, with variable overheads of ₹10,000. Annual output is 60,000 units, and the market price is ₹16 per unit. Management considers cutting batch size to 2,500 units. Material, labour and variable overhead per unit stay unchanged, and set-up cost per batch stays ₹2,500. What is the total cost per unit at 2,500-unit batches?
The total cost per unit is ₹13. Material, labour and variable overhead total ₹60,000 per 5,000 units, i.e. ₹12 per unit, which does not change. Set-up cost of ₹2,500 spread over 2,500 units adds ₹1 per unit, so cost is ₹12 + ₹1 = ₹13.
- A₹13.00Correct
- B₹12.50
- C₹12.00
- D₹13.50
Explanation
At 5,000 units: material, labour and variable overheads = 60,000 per batch = ₹12 per unit. At 2,500 units, these cost 12 per unit, and set-up is 2,500 / 2,500 = ₹1 per unit. Total = ₹13. Check: 2,500 × 12 = 30,000 + 2,500 = 32,500; 32,500/2,500 = 13. The ₹12.50 option wrongly keeps set-up per unit at the old ₹0.50.
Did you get it right without looking?
One question tells you little. A timed set on Unit & Batch Costing shows your real accuracy, how long you take and where you lose marks.
More Unit & Batch Costing questions
- Which of the following best describes a situation where batch costing is the appropriate costing method?
- Which of the following best describes the situation in which batch costing is the appropriate costing method?
- A manufacturer makes 2,000 units per batch. For one batch, the prime cost is Rs 3,20,000. Factory overheads are absorbed at 25% of prime cos…
- Kaveri Components makes a batch of 1,000 units. Batch cost is Rs 2,40,000. On inspection, 50 units are found defective in a way that is norm…
- Sharma Pens Ltd manufactures a batch of 2,000 pens. Direct materials cost Rs 40,000 and direct wages Rs 24,000. Factory overheads are absorb…
- Sundaram Cement Works produced 20,000 tonnes in a quarter. Costs were: raw materials ₹12,00,000; direct wages ₹4,00,000; factory overheads ₹…