Gupta Foods has a bottleneck of 1,800 hours. Product X earns throughput Rs 240 per unit using 2 bottleneck hours; Product Y earns Rs 270 per unit using 3 hours. Demand is 600 units of X and 500 units of Y. Operating expenses are Rs 1,20,000. What is the maximum net profit?

Maximum net profit is Rs 78,000, from 600 units of X and 200 units of Y, giving throughput of Rs 1,98,000 less operating expenses of Rs 1,20,000.

  1. ARs 1,20,000
  2. BRs 78,000Correct
  3. CRs 1,44,000
  4. DRs 96,000

Explanation

Throughput per bottleneck hour: X = 240/2 = Rs 120; Y = 270/3 = Rs 90. Rank X first. Make 600 units of X using 1,200 hours. Remaining 600 hours make 600/3 = 200 units of Y. Throughput = 600 x 240 + 200 x 270 = 1,44,000 + 54,000 = Rs 1,98,000. Less operating expenses of Rs 1,20,000 gives net profit of Rs 78,000.

Did you get it right without looking?

One question tells you little. A timed set on Throughput Accounting shows your real accuracy, how long you take and where you lose marks.

More Throughput Accounting questions